  • Current Status
    In construction - second phase Senior School is currently in progress.

TCPM is currently providing complete project management services through design, procurement, construction and hand-over, in addition to FF&E procurement for a three-phased full redevelopment of the existing school.

Design of the Junior School was completed in 2016.  Permitting and General Contractor tendering occurred from January to April 2017.  Construction commenced in May 2017 on a very active operating school site.

In the summer of 2016, TCPM also managed a complex portable classroom relocation on the site to create room for the Junior School expansion.

The Junior School opened in September 2018.  Construction of the second phase Senior School is currently in progress.